| Gate 0 · Foundation | Coupled QSS simulator, V0/V2/V1 verifier, B0–B2 baselines, deadline watchdog | Cross-platform test suite and verified non-vacuity / fail-closed safety invariants | Completed and archived (v0.1.0) |
|---|
| Gate 1 · Unseen Validation | Train: IEEE 30/39/57 · Fair-B2 Val: IEEE 118 & 300 (N = 40 scenarios, 720 runs) | ≥ 10% mean DNS reduction vs. best baseline (2.0 s) and paired bootstrap CI > 0 | Completed (v0.3.0 · GO): M1 36.161 vs. B2 54.391 MW (+33.5%, 0 VERIFIER_UNKNOWN) |
|---|
| Gate 2 · Blind PEGASE 1354 Scaling Test | Frozen Gate-1 weights tested zero-shot on PEGASE 1354 (CC BY 4.0, N = 20, zero tuning) | Zero-retraining transfer across 0.5 / 2.0 / 10.0 s budgets (360 verified runs) | Completed (v0.4.0): 10 s M1 10/20 (-39.3% trips, 669.4 MW) vs. B2 0/20; ~5.1 s > 2.0 s |
|---|
| Gate 3 · <2.0 s Sparse Path & Open-Science | Sparse PTDF on 1,354 buses, Zenodo DOI archive, and TSO offline demonstrator | End-to-end <2.0 s offline demonstrator ready for partner validation on anonymized models | Planned · next engineering & public artifact release cycle |
|---|