// Research Programme · Power Grid & SCADA Resilience

Research prototype · Synthetic IEEE reference grids · TRL 3 (self-assessed) · Partners soughtv0.4.0 · Gate 2 · Updated: 2026-11-22

SKOPION Power–SCADA Resilience

Offline decision-support module for transmission security teams when physical N-k contingencies coincide with partial SCADA observability and remote-control loss.

During coupled disturbances, transmission lines can trip simultaneously with regional SCADA concentrators or substation RTUs. Operators lose visibility into part of the grid while losing remote switching paths to generators and controllable loads. SKOPION evaluates which remedial actions remain physically and telemetrically actionable under tight compute deadlines.

Current status: TRL 3 research prototype validated on synthetic IEEE reference grids. Initial use targets strictly offline contingency studies, operator procedure drills, and Horizon Europe consortium preparation (2028–2030) — not autonomous live grid switching.

V0 / V2 / V1
Stateless verification gate before any approval
0.5 s / 2 s / 10 s
Equal wall-clock deadlines across all policies
B0–B3 vs. M1
Fair comparison against heuristic, MILP & GNN baselines
2028–2030
Target project window · HORIZON-CL3-2027-01-SSRI-01

The coupled grid–SCADA problem

Conventional N-k security tools assume full measurement freshness and unrestricted remote switching. When concentrator power drops and UPS reserves exhaust, telemetry freezes across affected zones. Standard optimizers unaware of dead actuator paths or stale load intervals either recommend unreachable devices or risk post-action thermal overloads.

Four architectural pillars

Every candidate selector — heuristic, classical MILP optimizer, or graph neural model — is judged inside the same coupled simulator and stateless verifier.

  1. 01 · COUPLED SIMULATOR

    Quasi-steady-state QSS Power ↔ SCADA engine

    Multi-island AC Newton-Raphson with reactive limits and distributed slack coupled to concentrator/RTU UPS timers in seconds, measurement staleness, inverse-time thermal relays, and discrete under-voltage load shedding.

  2. 02 · INDEPENDENT VERIFIER

    Fail-closed V0 / V2 / V1 checks with B0 fallback

    Separates proposal from proof: V0 enforces SCADA actuator reachability, V2 applies Z3 SMT verification over the linearized DC/PTDF uncertainty box, and V1 runs full AC Newton-Raphson at nominal and high-load corners.

  3. 03 · FAIR BENCHMARK HARNESS

    Disjoint topology splits against B0–B3

    Trained solely on IEEE 30/39/57, validated unseen in Gate 1 on IEEE 118/300 (+33.5% vs. Fair-B2 at 2.0 s), and tested blind with frozen weights (zero tuning) on PEGASE 1354 (CC BY 4.0) under identical V0/V2/V1 guardrails.

  4. 04 · ON-PREMISES DESIGN

    Deterministic deadline watchdog & air-gap readiness

    A hard wall-clock watchdog rejects any late proposal and hands control cleanly back to local protection (B0), engineered for local execution inside client analysis environments without cloud egress.

Interactive architecture and protocol view

Inspect the five-stage verification pipeline, the baseline-versus-candidate comparison matrix, and the Stage-Gate evaluation splits.

Fail-Closed → B0 Fallback1 · ObservationSTATE2 · V0 SCADAV03 · V2 SMT (DC)V24 · V1 AC NRV15 · WatchdogGUARD

Component: Telemetry & ActionSpaceMask

Coupled grid–SCADA state & staleness box U_t

Reads live switch states, last-known bus injections, and exact telemetry age per bus after concentrator/RTU outages without exposing future simulator states.

Pass requirement

Valid observed snapshot and explicit controllable-device mask constructed within budget.

Fail-closed rule

Any un-converged base step raises NUMERICAL_UNKNOWN without fabricated loss imputation.

Research log & Open-Science repositories

Gate 0–2 results are recorded here with SHA-256-verified bundles; code, datasets, and the versioned Zenodo DOI archive are staged for public release in the channels below alongside Gate 3 <2.0 s engineering.

  1. v0.3.0 · Gate 0–1 · 2026-11-19Completed

    Gate 1 Fair-B2 passed: +33.5% DNS reduction on unseen IEEE 118/300

    Completed symmetric Fair-B2 audit (N = 40 unseen scenarios, 720 runs, 0 VERIFIER_UNKNOWN): at 2.0 s, M1_coupled_hgnn reaches 36.161 MW vs. B2_highs_milp 54.391 MW (+33.5%, 95% CI [0.06, 43.67] MW, P95 129.6 <= 194.4 MW) → GO_UNLOCK_GATE2.

  2. v0.4.0 · Gate 2 · 2026-11-22Completed

    Blind zero-shot test on PEGASE 1354 (N = 20, zero tuning)

    Frozen Gate-1 weights (360 runs, 0 violations): at 0.5/2.0 s, single-thread CPU latency exceeds budgets for all selectors (fail-closed B0 743.2 MW). At 10.0 s, only M1 scales (10/20 approved, 5.07 s mean, -39.3% cascade trips 107 → 65, 669.4 MW) vs. B2 MILP 0/20 (16 timeouts) and B3/M1-Pure 0/20.

  3. Next · Gate 3 · 2026–2027Planned

    Gate 3: Sparse-PTDF (< 2.0 s), Zenodo DOI & TSO offline demonstrator

    Sparse-PTDF acceleration on 1,354 buses (~5.1 s → < 2.0 s single-thread), tighter preventive load-shed bounds, and public release of code, frozen split hashes, and versioned Zenodo DOI artifacts below.

Horizon Europe alignment & validation track (2028–2030)

The module is structured as an independent technical work package for European resilient-infrastructure consortia and bilateral offline TSO scenario studies.

Target European consortium and TSO validation tracks
Track / CallWindow & scopeSKOPION Intelligence contribution
HORIZON-CL3-2027-01-SSRI-01 (Resilient Infrastructure)Opening May 2027 · Deadline Nov 2027 · Indicative project window 2028–2030Focused SME work-package partner (EU PIC 861665939) delivering coupled Power–SCADA simulation and verified remedial action tooling
Internal R&D & National Matchmaking (NRW / Germany)2026–2027 · Reproducible Gate 0–3 engineering foundationVerification harness, multi-baseline comparison protocol, and anonymized grid ingestion interfaces
Bilateral TSO / Control-System Integrator Offline PilotFollowing Gate 3 sparse-PTDF (<2.0 s) & artifact releaseParallel offline shadow studies on anonymized utility models with explicit counterexample logs

Registered EU Participant Identification Code: PIC 861665939 (Skopion Intelligence, Mönchengladbach, Germany). Funding references indicate call alignment and partner-search intent, not an awarded grant or established consortium.

Work-package contribution for consortium coordinators

For coordinators in power engineering, grid operations, or research institutes, SKOPION scopes a self-contained technical package:

  • Coupled physical grid and SCADA UPS/latency contingency simulation environment
  • Stateless candidate verification gate (SCADA mask, bounded Z3 DC box, and two-corner AC Newton-Raphson)
  • Equal-budget multi-baseline benchmarking harness (heuristic, MILP, simple GNN vs proposed models)
  • Locally deployable Python/container module built for air-gapped utility engineering environments

Partners sought for validation

To bridge synthetic IEEE benchmarks and real utility planning needs, we invite discussions with:

  • Transmission or distribution system operator (TSO / DSO) operational-planning and security teams
  • EMS / SCADA control-system integrators advising on realistic telemetry failure and command-delay bounds
  • Academic and industrial coordinators forming consortia for Horizon Europe Cluster 3 SSRI (2028–2030)

Explicit scope limits

  • —Quasi-steady-state (QSS) AC modelling only — excludes electromagnetic transient (EMT) or sub-second rotor-angle dynamics
  • —Validated to date exclusively on synthetic IEEE reference grids; no proprietary operator data in current artifacts
  • —Formal Z3 SMT verification (V2) strictly covers the linearized DC/PTDF box; AC nonlinearity is checked at two corners in V1
  • —On 1,354 buses the single-thread dense-PTDF path averages ~5.1 s (missing the 2.0 s deadline), and wide U_t uncertainty boxes caused 39–95 MW extra preventive curtailment in 5/10 Gate-2 runs — both targeted in Gate 3

On-premises execution architecture (Reference Node R1)

For isolated offline deployment inside utility security boundaries, the companion Sovereign AI Security Node R1 project defines an air-gapped workstation target architecture.

View Reference Node R1

SKOPION Navigator

Zero-LLM · Deterministic

No language model, no prompt injection, no external egress — deterministic server rules & live site feeds.

Ask directly about services, NIS2/CRA/EU AI Act, NRW MID funding, live Cyber Situation advisories, Cyber Calendar, or the Regional Atlas.

Quick prompts

Want a Zero-LLM assistant like this on your site?Request integration